Projects
Our Projects
Hundreds of projects executed across our different activity sectors spanning a multitude of services.
14 District Digital Control Centers Upgrade (14DCC)
Activity SectorControl Centers & SCADA Systems
LocationEgypt
End ClientEgyptian Electricity Holding Company (EEHC)
Completion DateRunning
Technology PartnerSchneider Electric
Client ConsultantDNV (for North Cairo Electricity Distribution Company - Phase 1)
Lahmeyer (for South Cairo Electricity Distribution Company - Phase 1)
Lahmeyer (for South Cairo Electricity Distribution Company - Phase 1)
ServicesEPC, Testing, Commissioning & Start-up
PackageTurnkey Electrical Package
Al Fajij 220KV AIS Substation Extension
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerAlstom
ServicesEPC, Testing, Commissioning & Start-up, Supervision
Tobruk 4 x 175MW Simple Cycle Power Plant
Activity SectorPower Plants - Simple Cycle Gas Turbine Power Plants
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerGeneral Electric (Units 1 & 2) Ansaldo Energia (Units 3 & 4)
Client ConsultantArabian Consultancy Engineering Services Company (ACESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageInstrumentation & Control, Mechanical and Electrical Installation, Start-up Works
Sabha 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Tobruk 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Bany Walid 500KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Hoon 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Al Beida 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Hay El Salam 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientEgyptian Electricity Transmission Company (EETC)
Completion DateRunning
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
GECOL Building 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion DateRunning
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Civil, Inland Logistics, MEP, Security, Testing, Commissioning & Start-up, Supervision
Janzour Center 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2022
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Civil, Inland Logistics, MEP, Security, Testing, Commissioning & Start-up, Supervision
ASORC Naphta Complex 220/11/11KV GIS Substation
Activity SectorPetrochemical Facilities
LocationEgypt
End ClientAssiut Oil Refining Company (ASORC)
Completion Date2021
Technology PartnerGeneral Electric
Client ConsultantEnppi
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Suez 500KV AIS Substation Extension
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – AIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2021
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Assiut East 66/22/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2021
Technology PartnerSieyuan Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Madinaty 2 220/66/22KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2021
Technology PartnerSieyuan Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Obari 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2021
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Civil, Inland Logistics, MEP, Security, Testing, Commissioning & Start-up, Supervision
Lusail Underground Light Rail Transit (LRT)
Activity SectorRailways
LocationQatar
End ClientQatar Railways Company
Completion Date2020
Technology PartnerAlstom Transport
ServicesProcurement, Mechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
New National Energy Control Center (N-NECC)
Activity SectorControl Centers & SCADA Systems
LocationEgypt
End ClientEgyptian Electricity Holding Company (EEHC)
Completion Date2020
Technology PartnerSiemens
Client ConsultantEDF Energy
ServicesConsultancy: Design & Engineering, Consultancy: Project Management
PackageConsultancy for Siemens for Building Works During Tendering Stage
Nubaria III 1 x 750 MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientMiddle Delta Electricity Production Company
Completion Date2020
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
South Helwan 3 x 650 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientUpper Egypt Electricity Production Company (UEEPC)
Completion Date2020
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Al Shabab 2 x 750 MW Combined Cycle Add-on Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2020
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageInstrumentation & Control, Package 1: Electrical, Start-up Works
Al Shabab 2 x 750 MW Combined Cycle Add-on Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2020
Technology PartnerAC Boilers
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackagePackage 2: Heat Recovery Steam Generator Works
El Khoms 11 Gas Turbine Units Simple Cycle Power Plant
Activity SectorPower Plants - Simple Cycle Gas Turbine Power Plants
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2020
Technology PartnerABB
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
West Damietta 1 x 750MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2020
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageInstrumentation & Control, Package 1: Electrical, Start-up Works
West Damietta 1 x 750MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2020
Technology PartnerAC Boilers
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackagePackage 2: Heat Recovery Steam Generator Works
Temai Emdeed 500/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2020
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ismalia East 500/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2020
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Beni Sweif 500/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2019
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Zohr Gas Field Energy Control System
Activity SectorPetrochemical Facilities
LocationEgypt
End ClientBelayim Petroleum Company (PetroBel)
Completion Date2018
Technology PartnerSchneider Electric
Client ConsultantEni
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Mostathmereen 220/66KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2018
Technology PartnerGeneral Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Mall of Egypt
Activity SectorCommercial Buildings
LocationEgypt
End ClientMajid Al Futtaim Group
Completion Date2017
Technology PartnerSchneider Electric
ServicesMEP
Irqah 380/132/13.8KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2017
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Training Program for Solar Power Installation
Activity SectorRenewable Energy – Solar Power
LocationEgypt
Completion Date2017
Technology PartnerSun Power
ServicesMechanical Installation, Electrical Installation
Al Nahda 132/13.8KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2017
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Maazalia 132/138.8KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2017
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Zamel 132/13.8KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2017
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Ortawia 132/13.8KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2017
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Qatar National Bank (QNB) Al Ahli Data Center
Activity SectorData Centers
LocationEgypt
End ClientQatar National Bank (QNB) Al Ahli
Completion Date2016
Technology PartnerSchneider Electric
ServicesEPC
Giza North 750MW Module III Combined Cycle Power Plant Extension
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientCairo Electricity Production Company (CEPC)
Completion Date2016
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
West Damietta 500MW Simple Cycle Power Plant (Fast Track)
Activity SectorPower Plants - Simple Cycle Gas Turbine Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2016
Technology PartnerGeneral Electric
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
New Assiut 1000MW Simple Cycle Power Plant (Fast Track)
Activity SectorPower Plants - Simple Cycle Gas Turbine Power Plants
LocationEgypt
End ClientUpper Egypt Electricity Production Company (UEEPC)
Completion Date2016
Technology PartnerGeneral Electric
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Mahmoudia 330 MW Simple Cycle Power Plant (Fast Track)
Activity SectorPower Plants - Simple Cycle Gas Turbine Power Plants
LocationEgypt
End ClientWest Delta Electricity Production Company (WDEPC)
Completion Date2016
Technology PartnerGeneral Electric
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Al Shifa 132/33KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2016
Technology PartnerMultiple Suppliers Procured
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Wagba Super 220/132/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationQatar
End ClientKahramaa
Completion Date2016
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tripoli South 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2016
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
El Tabba 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2016
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Giza North 2 x 750MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientCairo Electricity Production Company (CEPC)
Completion Date2015
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Banha 1 x 750 MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientMiddle Delta Electricity Production Company
Completion Date2015
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Ain El Sokhna 2 x 650 MW Steam (Supercritical) Power Plant Units 1 & 2
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2015
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Umm Bab 132/33/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationQatar
End ClientKahramaa
Completion Date2015
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Lusail Development Super-2 400/220/66/11KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationQatar
End ClientKahramaa
Completion Date2015
Technology PartnerAreva
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tripoli West 220KV AIS Substation Rehabilitation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2014
Technology PartnerAlstom
ServicesEPC, Testing, Commissioning & Start-up
Ghadames PS#1 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2014
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ghadames PS#2 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2014
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ghadames PS#3 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2014
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Zweitina 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2014
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Madina FSC 380/33KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2014
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abu Qir 2 x 650 MW Steam (Supercritical) Power Plant Units 6 & 7
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientWest Delta Electricity Production Company (WDEPC)
Completion Date2013
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
El Galaa 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2013
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abu Arqoub 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2013
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Sarir 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2013
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Upgrading of Misurata Steam Factory 2 x 300 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationLibya
End ClientMisurata Steel Factory (LISCO)
Completion Date2012
Technology PartnerABB
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Ghadames 400/66KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2012
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Ruwais 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2012
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Egyptian British Hatcheries
Activity SectorIndustrial Facilities
LocationEgypt
End ClientMinistry of Agriculture and Land Reclamation (MALR)
Completion Date2010
Technology PartnerBarco International Inc.
ServicesProcurement, Mechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
West Delta Regional Control Center (WDRCC)
Activity SectorControl Centers & SCADA Systems
LocationEgypt
End ClientEgyptian Electricity Holding Company (EEHC)
Completion Date2010
Technology PartnerAlstom
Client ConsultantEDF Energy
ServicesTurnkey
PackageBuilding Works
Rehabilitation of Aswan High Dam 12 x 175MW Hydro Power Plant
Activity SectorRenewable Energy – Hydro Power - Large Scale Hydro Power Plants
LocationEgypt
End ClientUpper Egypt Electricity Production Company (UEEPC)
Completion Date2010
Technology PartnerVoith Siemens - Power Machines JV
Client ConsultantSweco
ServicesTurnkey
Gulf HVDC Interconnection
Activity SectorPower Grid Facilities – Transmission Lines - HVDC
LocationKingdom of Saudi Arabia, Kuwait, Qatar
End ClientSaudi Electricity Company (SEC)
Completion Date2010
Technology PartnerAreva
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Fadhili HVDC Back – to – Back Converter Stations
Activity SectorPower Grid Facilities – Transmission Lines - HVDC
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2010
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
7 x 220KV AIS Substations Rehabilitation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Misurata 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abu Fakher 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Benghazi South 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Janzour 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up, Supervision
Sirte 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2010
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Shuqaiq 380/132/13.8KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2010
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abha East 380/132KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2010
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gamra – Ghadames – Zewra Line PS #1 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra – Ghadames – Zewra Line PS #2 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra – Ghadames – Zewra Line PS #3 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra – Ghadames – Zewra Line PS #4 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Zeraa 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Stadium 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tabba 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Agdabia 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2009
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Ras Lanouf 400KV Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2009
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Cairo North II 1 x 750 MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientCairo Electricity Production Company (CEPC)
Completion Date2008
Technology PartnerNEM
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageHeat Recovery Steam Generator Works
Sirte National Control Center (SNCC)
Activity SectorControl Centers & SCADA Systems
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerAlstom
Client ConsultantEDF Energy
ServicesMechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
PackageMicrowave Tower, SCADA System Installation & Adaptation Works
Tripoli National Control Center (TNCC)
Activity SectorControl Centers & SCADA Systems
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerAlstom
Client ConsultantEDF Energy
ServicesMechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
PackageMicrowave Tower, SCADA System Installation & Adaptation Works
Tripoli Regional Control Center (TRCC)
Activity SectorControl Centers & SCADA Systems
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerAlstom
Client ConsultantEDF Energy
ServicesMechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
PackageMicrowave Tower, SCADA System Installation & Adaptation Works
Doha Industrial 132 E 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationQatar
End ClientKahramaa
Completion Date2008
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abu Sidra North 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationQatar
End ClientKahramaa
Completion Date2008
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gamra – Rabta – Abu Zayan Line Rabta 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra – Rabta – Abu Zayan Line – PS #1 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra – Rabta – Abu Zayan Line – PS #2 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Zleiten 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gulf 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Fashloum 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Zawia 400KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Bir Austa Milad 400/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2008
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Cairo North I 1 x 750 MW Combined Cycle Power
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientCairo Electricity Production Company (CEPC)
Completion Date2007
Technology PartnerMultiple Suppliers Procured
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageInstrumentation & Control, Package 1: Electrical, Start-up Works
Cairo North I 1 x 750 MW Combined Cycle Power
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
Completion Date2007
Technology PartnerNEM
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackagePackage 2: Heat Recovery Steam Generator Works
Sedi Hamed 220KV GIS Substaion
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2007
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
DIE-3A 69/13.8KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationKingdom of Saudi Arabia
End ClientSaudi Electricity Company (SEC)
Completion Date2006
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Attaka 1 x 150 MW + 2 x 300 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2005
Technology PartnerEmerson USA
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Abu Sultan 4 x 150 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2005
Technology PartnerHoneywell USA
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Abu Qir 4 x 150 MW Steam (Supercritical) Power Plant Upgrade
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientWest Delta Electricity Production Company (WDEPC)
Completion Date2005
Technology PartnerHoneywell USA
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
El Lahoun 2 x 400KW Mini Hydro Power Plant
Activity SectorRenewable Energy – Hydro Power – Mini Hydro Power Plants
LocationEgypt
End ClientUpper Egypt Electricity Production Company (UEEPC)
Completion Date2005
Technology PartnerAlstom
ServicesTurnkey
El Zafarana 2 1 x 100 MW Wind Farm Power Plant
Activity SectorRenewable Energy – Wind Farms
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2005
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageInstrumentation & Control, Mechanical and Electrical Installation, Start-up Packages
Libya National Control Centers OPGW Project
Activity SectorControl Centers & SCADA Systems
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2005
Technology PartnerAlstom
Client ConsultantEDF Energy
ServicesMechanical Installation, Electrical Installation, Civil, In-land Transportation, MEP, Testing, Commissioning & Start-up
PackageBuilding Works, SCADA System Installation & Adaptation Works
12 x 30/11KV GIS Substations
Activity SectorPower Grid Facilities – Substations – GIS – 30KV or 22KV Ratings
LocationLibya
End ClientElectrical Projects Company (ELPCO)
Completion Date2005
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Cairo 500KV AIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – AIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2005
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Benghazi Central 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2005
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Zawya 220/30KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2005
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Azhar Tunnel
Activity SectorTunnels
LocationEgypt
End ClientEgypt's Ministry of Transport
Completion Date2004
Technology PartnerCampenon Bernard (Tunnel Feeders)
Spie Enertrance (Tunnel Works)
Spie Enertrance (Tunnel Works)
ServicesElectrical Installation, Testing, Commissioning & Start-up
Motobas 66/11KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2004
Technology PartnerSchneider Electric
ServicesEPC, Testing, Commissioning & Start-up
Ben Ghashier 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Zwarah 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Zlieten 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tripoli Bottling Company 11/0.4KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 11KV Ratings or Less
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ras Lanouf 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Benghazi North 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2004
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Fassy 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Zlieten University 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Boaishy 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Obari 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Fajij 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Traghen 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2003
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Sheikh Zayed Pumping Station
Activity SectorEnvironmental & Sanitation Systems – Pump Stations
LocationEgypt
End ClientMinistry of Water Resources and Irrigation
Completion Date2002
Technology PartnerBalfour Kilpatrick
ServicesProcurement, Mechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
Al Gharbeyat 66KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
ServicesEPC, Testing, Commissioning & Start-up
Al Kusair 66KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
ServicesEPC, Testing, Commissioning & Start-up
Abu Eissa 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Hira 30KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Orouba 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tobrok 220/66/11KV GIS Substation Extension
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2002
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ain El Seira 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2002
Technology PartnerHyundai
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
(34-36) 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Janzour 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Mangoub 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Halab Street 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abou Zian 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gabal El Asfar Wastewater Treatment Plant
Activity SectorEnvironmental & Sanitation Systems – Wastewater Treatment Plants
LocationEgypt
End ClientConstruction Authority for Potable Water and Wastewater (CAPW)
Completion Date2001
Technology PartnerBalfour Kilpatrick
ServicesMechanical Installation, Electrical Installation
Sebha – Hamza Agricultural Project 66KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Ajdabia – Tobruk Road 66/11KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Sebha El Gadid 66/11KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Jaref 66/11KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Al Qurdabia – Sirte 66/11KV AIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – AIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2001
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Cairo East 220KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2001
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Sabtia 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2001
Technology PartnerSchneider Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tripoli 11KV & 30KV 97Km Network
Activity SectorPower Grid Facilities – Transmission Lines – MVAC
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
Beer El Abd 220/66/22KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2000
Technology PartnerMitsubishi Electric
ServicesEPC, Testing, Commissioning & Start-up
Ayoun Moussa 2 x 320 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date2000
Technology PartnerBalfour Beatty Kipatrick
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Sidi Krir 2 x 320 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientWest Delta Electricity Production Company (WDEPC)
Completion Date2000
Technology PartnerCEGELEC
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesEPC, Testing, Commissioning & Start-up
PackageElectrical, Instrumentation & Control, Start-up Works
Bab Tarhona, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Souq Al Qoubab, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Saha El Shabia, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Benghazi End 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Civil, MEP, Testing, Commissioning & Start-up
Gamra 1 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gamra 2 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gemines 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date2000
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ayoun Moussa 500/220KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date2000
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Hadaek, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1999
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Rousat, Benghazi 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1999
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Sidi Eissa, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1999
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Port Said East 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1999
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Greater Cairo Metro Line 2 Phases 1A, 1B, 2A & 2B
Activity SectorRailways
LocationEgypt
End ClientEgyptian National Railways (ENR)
Completion Date1998
Technology PartnerSpie Enertrance
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Hadaba, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1998
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Menna, Benghazi 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1998
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Libya Bank, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1998
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tyeba 500/400/220/132/22KV AIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – AIS – 500KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1998
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ghaza North 220/22KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationPalestine
End ClientPalestinian Energy Authority
Completion Date1998
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ghaza West 220/22KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationPalestine
End ClientPalestinian Energy Authority
Completion Date1998
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tripoli Road, Benghazi 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1997
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
The Great Man-Made River, Benghazi 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGreat Man Made River Authority (GMMRA)
Completion Date1997
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Gamahira Street, Tripoli 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1997
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Amman South 400/132/33KV AIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – AIS – 500KV
LocationJordan
End ClientNational Electric Power Company (NEPCo) Jordan
Completion Date1997
Technology PartnerSchneider Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Wadi El Nakra 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1997
Technology PartnerAlstom
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Sidi Krir 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1997
Technology PartnerSchneider Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Stadium 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1997
Technology PartnerMerlin Gerin
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Al Arish 1 x 300 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientEast Delta Electricity Production Company (EDEPC)
Completion Date1996
Technology PartnerNouva Cimi Montoubi
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
El Wallidia New Assiut 1 x 300 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientUpper Egypt Electricity Production Company (UEEPC)
Completion Date1996
Technology PartnerABB
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Station No. 1, Benghazi 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1996
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Ras Lanouf 30/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 30KV or 22KV Ratings
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1996
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Tobruk 3.3KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 11KV Ratings or Less
LocationLibya
End ClientGeneral Electricity Company of Libya (GECOL)
Completion Date1996
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Greater Cairo Metro Line 2 Workshop Facilities
Activity SectorRailways
LocationEgypt
End ClientEgyptian National Railways (ENR)
Completion Date1996
Technology PartnerSpie Enertrance
ServicesMechanical Installation, Electrical Installation, Operation & Maintenance, Testing, Commissioning & Start-up
El Sallum 220KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1996
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Sadat 220KV AIS Substation Extension
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1996
Technology PartnerSchneider Electric
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Siuf 220/66/11KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1996
Technology PartnerMitsubishi Electric
ServicesEPC, Testing, Commissioning & Start-up
El Bassateen to Wadi Hoof 66KV 25Km Overhead Transmission Line
Activity SectorPower Grid Facilities – Transmission Lines - HVAC
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1995
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Civil, Testing, Commissioning & Start-up
Cairo West 2 x 320 MW Steam (Supercritical) Power Plant
Activity SectorPower Plants - Steam (Supercritical) Power Plants
LocationEgypt
End ClientCairo Electricity Production Company (CEPC)
Completion Date1995
Technology PartnerABB
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageElectro-Mechanical Installation, Instrumentation & Control, Start-up Works
Damanhour 4 x 50 MW Combined Cycle Power Plant
Activity SectorPower Plants - Combined Cycle Power Plants
LocationEgypt
End ClientMiddle Delta Electricity Production Company
Completion Date1995
Technology PartnerNEM
Client ConsultantPower Generation, Engineering & Services Company (PGESCo)
ServicesProcurement, Mechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
PackageHeat Recovery Steam Generator Works
New Beni Suef 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1995
Technology PartnerSiemens
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Arish 220/22KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1995
Technology PartnerSprecher Energie
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Walidia – Assiut 220KV GIS Substation
Activity SectorPower Grid Facilities – Substations – GIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1995
Technology PartnerABB
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Dokki 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1994
Technology PartnerMerlin Gerin
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Ahleya Abu Zaabal 66/11KV GIS Substation
Activity Sector66KV or 60KV Ratings, Power Grid Facilities – Substations – GIS – 69KV
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1994
Technology PartnerMerlin Gerin
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
El Bostan 220/66/11KV AIS Substation
Activity SectorPower Grid Facilities – Substations – AIS – 220KV & 132KV Ratings
LocationEgypt
End ClientEgyptian Electricity Transmission Company (EETC)
Completion Date1994
Technology PartnerIsolux Wat
ServicesMechanical Installation, Electrical Installation, Testing, Commissioning & Start-up
Abu Zaabal 500/220/66/11KV GIS Substation
Activity Sector400KV & 380KV Ratings, Power Grid Facilities – Substations – GIS – 500KV
LocationEgypt